From Vision to Reality

The Warwick High School Projects consist of the phased construction of new Pilgrim High School and Toll Gate High School, including modern academic facilities, career and technical education spaces, performing arts venues, athletic facilities, site and utility improvements, parking and circulation upgrades, environmental mitigation measures, and associated campus infrastructure. The projects are designed to provide safe, sustainable, and flexible learning environments that support 21st-century educational programming while enhancing community use and long-term operational efficiency.

Projects at a Glance

October 2027

Toll Gate Building Completion

54%

Construction Completion

$350M

Project Budget

March 2028

Pilgrim Building Completion

Construction start delayed for environmental mitigation measures


41%

Construction Completion

Project Scope (Included in the $350M)

Two new high school buildings

Interior renovation at the CTC Building

Demolition of existing high school buildings

New parking and circulation improvements

Utility infrastructure upgrades

Site grading and landscaping

Sustainable building features and energy-efficiency measures

New turf multipurpose fields with bleachers, press boxes, and lighting at both schools

New grass multipurpose practice field at Toll Gate

New furniture, equipment, interactive classroom displays, and network infrastructure

Architectural, engineering, and project management fees

Project Alternates

Financial Highlights

  • Over $1.5M in GMP Allowances returned to Warwick to date

  • Approximately $1M of Toll Gate CM Contingency forecasted to return to Warwick

  • Post-GMP net contract growth is tracking below market average

GMP Allowances

Pre-budgeted amounts for known or anticipated scope elements not fully defined at the time of GMP establishment.

Any amounts that are eventually confirmed to be unneeded are returned to Warwick.

CM Contingency

Managed by the CM; covers unforeseen construction costs, coordination issues, and constructability adjustments.

Any amounts that are eventually confirmed to be unneeded are returned to Warwick.